Construction of Australia's first Frank Gehry building proceeds apace!

Concrete slabs have been poured to level 8 (where the building will step in and become narrower), with the jump form now reaching level 12 (the top occupied floor)

The substrate panels (which will sit behind the brickwork) have been installed into a series of curved, concrete hobs (guides) to level 2. (See image top right)

All formwork has been stripped to level 2. Levels 3-5 are progressing