Hellisheidi geothermal power plant is a flash steam, combined heat and power plant (CHP) located in SW-Iceland, on one of the largest wet geothermal systems (high-enthalpy) in Iceland. The plant’s purpose is to meet increasing demand for electricity and hot water for space heating. The development plan was an incremental or phased expansion from 2006 to 2011 to an output of 303 MWe and 133 MWth, making it the largest geothermal combined heat and power plant in Iceland. The plant owner is Orkuveita Reykjavíkur.

The first phase included two high-pressure 45 MWe turbines that went online in October, 2006 and then one low pressure 33 MWe turbine went online in Fall, 2007. The next expansion phase consisted of two additional 45 MWe turbines that went online in Fall, 2008. The first stage (133 MWth) of three thermal power plants was commissioned in 2010. The final phases will put the thermal capacity at 400 MWth. Overall, 50 boreholes were drilled, from 1,000-2,200 meters.The last power expansion (phase 5) adding 2 x 45 MWe, went online in 2011, where Project Management, HVAC, mechanical design, control systems, commissioning and training was also handled by Mannvit.

Hellisheidi Geothermal Power Plant details:

Flash steam, combined cycle power plant
Planned total output: 303MWe & 400MWth
Phase 1: 2 x 45 MWe
Phase 2: 33 MWe
Phase 3: 2 x 45 MWe
Phase 4: First stage thermal power plant
Phase 5: 2 x 45 MWe
50 boreholes were drilled, from 1,000-2,200 meters

Mannvit services:

Project management
Overall plant design
Environmental impact assessment
Detailed mechanical design of the plant
Detailed design of HVAC systems
Bid preparation and tender evaluation
Site supervision
Commissioning
Acceptance test
Training of operators
EIA scoping report
Environmental modelling
Reservoir engineering
Design of control systems