Under the direction of MassDOT the most ambitious highway replacement project to date took place during the Summer of 2011 along I-93 in the town of Medford, Massachusetts just outside of Boston, MA.

The 93Fast14.org project replaced 14 4-lane interstate I-93 highway bridges in just 10 weekends under the joint venture of Kiewit Construction and J.F. White Contracting Co.

A typical 55-hour weekend closure began at 10PM on Friday night and ended at 5 AM on Monday morning. Each weekend went exactly according to plan despite unusually heavy traffic into Boston early on to celebrate the win of the Boston Bruins Stanley Cup Finals and subsequent victory parade.

Phase 1: Reroute and redirect traffic

Phase 2: Completely demolish and remove each 4 lane, 3 span interstate bridge in its entirety

Phase 3: Install precast re-bar reinforced modular concrete panels, making up the new bridge deck.

Phase 4: Tie the panels together using an interlacing rebar

Phase 5: Pour concrete, making the concrete deck one seamless section.

Phase 6:re-open high way and redirect traffic onto new bridge.

# vimeo.com/34043623 Uploaded 548 Plays 0 Comments

Follow

LABOR DAY TRIBUTE

Stephen SetteDucati PRO

A Collection of Videos Honoring the Men and Women that work hard day in and day out shedding blood, sweat and tears to help build America.

Shout Box

Heads up: the shoutbox will be retiring soon. It’s tired of working, and can’t wait to relax. You can still send a message to the channel owner, though!

Channels are a simple, beautiful way to showcase and watch videos. Browse more Channels.